UK Reveals Schedules of Selected Weapon Programs
(Source: Defense-Aerospace.com; posted April 08, 2019)
The Crowsnest airborne early warning variant of the AgustaWestland Merlin Mk 2 was due to make its first flight by March 31, and even though it was not announced, photos of its first flight began circulating on social media in early April. (Twitter photo)
PARIS --- Britain’s Ministry of Defence has released letters of appointment for the Senior Responsible Owners (SROs) for Government Major Projects Portfolio (GMPP).

With notable exceptions, these letters provide some information about the timescales of the programs that these SROs are required to meet. Some of these milestones had not been previously made public, some had been but only partly, and some not at all.

We have extracted the main milestones for the largest programs, and reproduced them below. Note that some of the milestones were partly or entirely blacked out.


A400M:
-- Initial Support to Tactical Operations — June 2019.
-- Enhanced Support to Tactical Operations — June 2020.
-- Long-Range Maritime Assistance — April 2021.
-- Support to Specialist Users — April 2022.
-- Operations in Contested Environments — September 2022.
-- Final (22nd) Aircraft Delivery — November 2022.


CROWSNEST:
-- First Flight of CROWSNEST Programme –31 March 2019.
-- Conclusion of Flight Trial Activity required to support initial Aircrew Training –30 September 2019.
--Commence delivery of Aircrew Training (associated with the deterministic date for the System Training Milestone) –10 October 2019.
-- Achieve delivery of the Airborne Surveillance & Control Mission Trainer to realise Ready 31for Training Date (Number 6) –14 November 2019


FLEET SOLID SUPPORT
-- Receipt of Initial Tender Returns from Bidders -31 July 2019.
-- Initial Bid Evaluation Complete -31 October 2019.
-- Conduct IPA Gateway 4 Review Prior to Main Gate -30 November 2019.
--Submit Main Gate Business Case to Business Case Review Board -31 December 2019.


FUTURE MARITIME SUPPORT
-- Competition phase: Start of Pre-Qualification process -August 2018
-- Issue Invitation to Tender/Negotiate -October 2018
-- Submit Main Gate Business Case to Investment Appraisal Committee -September 2019
-- FMSP Contact Award -November 2019


MARITIME PATROL AIRCRAFT
-- Introduction to Service first UK aircraft: April 2019
-- Preparation of Infrastructure at RAF Lossiemouth: August 2019


PROTECTOR
-- Delivery of maintainer & operator training in US: May 2019
-- Delivery of Interim Release to Service: May 2019
-- Acceptance of program infrastructure: September 2019


Click here for the SRO appointment letters, on the MoD website.

-ends-







prev next