NNSA Has Taken Steps to Prepare to Restart a Program to Replace the W78 Warhead Capability
U.S. Government Accountability Office (GAO)
GAO-19-84
Nov 30, 2018
The Department of Energy's National Nuclear Security Administration (NNSA) has taken steps to prepare to restart a life extension program (LEP) to replace the capabilities of the Air Force's W78 nuclear warhead—a program which was previously suspended. According to NNSA officials, these steps are typically needed to conduct any LEP. Therefore, they can be undertaken despite the current uncertainty about whether the final program will develop the warhead for the Air Force only or for both the Air Force and the Navy. Specifically, NNSA has taken the steps described below:

-- Program management. NNSA has begun to establish the program management functions needed to execute a W78 replacement program, as required by NNSA's program execution instruction. For example, NNSA has started to develop a risk management plan to define the process for identifying and mitigating risks. In addition, NNSA has created a preliminary schedule to restart the program in fiscal year 2019 in the feasibility and design options phase with the goal of producing the first unit in fiscal year 2030. (See figure)

-- Technology assessment. In May 2018, NNSA completed an assessment of 126 technologies for potential use in a W78 replacement. These included nine technologies that are needed to replace obsolete or no longer available technologies or materials. These are considered “must-do” because they are the only technologies or materials available to meet minimum warhead requirements established by the Department of Defense and NNSA. NNSA officials said that in fiscal year 2019 they will use the assessment to further evaluate technologies for potential use in the warhead.

-- Coordination with facilities and capabilities. NNSA's program manager is identifying the facilities and capabilities needed to provide components for the warhead. This information will be used to produce a report that identifies aspects of the program—including facilities and capabilities to support it—that could affect the program's schedule and technical risk. However, several of the needed facilities must be built or repaired, and these activities are separately managed and supported outside the W78 replacement program—representing a critical external risk to the program. As mitigation, the program intends to coordinate with the offices that oversee these facilities to draft agreements that describe the work to be performed and timeframes, among other things.